An engineer must perform a predictive design for a wireless network. The customer has devices that can tolerate at most 100 ms of delay when roaming. Which design criteria must be used?
Refer to the exhibit.
A client roams between two APs that are registered to two different controllers, where
each controller has an interface in the client subnet. Both controllers are running AireOS. Which scenario explains the client roaming behavior?
Which two criteria must be considered when conducting an outdoor bridge site survey? (Choose two.)
An engineer is trying to configure the APs installed in a new auditorium to use 40 MHz channels with high data rates and lower TX power. The APs in the building hallway must use lower-density design settings configured for the rest of the building. Which two configurations achieve this design? (Choose two.)
An engineer is conducting a Layer 2 site survey. Which type of client must the engineer match to the survey?
A wireless engineer is performing a post verification of a wireless network. Which two metrics does the engineer verify to ensure that the wireless network can support voice services? (Choose two.)
An engineer performs a Layer 1 survey by using Metegeek chanalyzer only on the current operating channel. Which operating mode is configured for a Cisco CleanAIR AP?
An engineer added an AP to a deployment after a post-installation site survey. The engineer then notices an increase in co-channel interference and retransmissions. Which two features help mitigate the issue? (Choose two.)
A customer is running a guest WLAN with a foreign/export-anchor setup. There is one anchor WLC in the US and two in Europe. Anchor WLC priorities are used to prefer local anchors. During a routine network audit, it is discovered that a large number of guest client sessions in the US are anchored to the WLCs in Europe. Which
reason explains this behavior?
Refer to the exhibit.
An engineer is about to establish a mobility peer connection between a Cisco Catalyst 9800-CL version 16.10.1e and Cisco AireOS 5520 version 8.8.120.0. The data path between the 9800-CL and AireOS 5520 is down, but its control path is up. Based on the configuration, what is the cause of the issue?