Questions # 21:

Cleo is a Project Manager and is drafting a set of objectives for her project. She has decided that the project must have completed stages 1 and 2before the end of the financial year. This is an example of what type of objective?

Options:

A.

achievable


B.

relevant


C.

specific


D.

time-bound


Expert Solution
Questions # 22:

Which of the following is a‘push’strategy for change?

Options:

A.

coercion


B.

collaboration and communication


C.

goal-orientated change


D.

refinement


Expert Solution
Questions # 23:

Parker Incorporated is launching a new product which customers will never have seen before. As it is completely unknown to the marketplace, which type of change situation is to be expected?

Options:

A.

predicted change


B.

closed change


C.

contained change


D.

open-ended change


Expert Solution
Questions # 24:

Ali is a Project Manager at a large retail organisation within the UK. He has created a project timeline and allocated a budget. However, two months into the project the UK declares a national lockdown due to an unknown virus sweeping the nation. What type of complexity is this known as?

Options:

A.

structural complexity


B.

technical complexity


C.

directional complexity


D.

temporal complexity


Expert Solution
Questions # 25:

Screwdriver Ltd runs a Lean manufacturing process and has recently sequenced its supply chain. It discovered that there is an average two-day delay between the completion of task 1 and task 2. What type of cost is this?

Options:

A.

interchange cost


B.

direct cost


C.

indirect cost


D.

dependency cost


Expert Solution
Questions # 26:

What is the purpose of completing aProject Reviewat the end of a project?Select TWO

Options:

A.

to assign blame for areas that did not go well


B.

for team members to reflect on what they learned during the project


C.

to understand long-term changes the project might create


D.

to satisfy a demand from senior leadership


Expert Solution