When completing arisk assessment, which TWO characteristics of a risk should bequantitativelyexamined?
Freeman defines six stakeholder categories who are able to influence the success of a project.Select THREE
Daniel is a Project Manager and has just run a risk simulation to find out the likelihood of his project taking 3, 4, or 5 weeks to complete. He discovered it isequally likelythe project would take any of those durations. What type of distribution is this?
Zoe is a Manager at Friends Incorporated. The company is undergoing a major change to working practices, and Zoe has noticed that several of her team seem cynical about the changes. What should Zoe do?Select TWO
In Lewin's 3 stage Change Model, which is the first stage?
Which of the following is an example of an exogenous disruption that stimulates the requirement for change within an organisation?
What is the purpose of theproject controlstage within the project lifecycle?
Which model maps stakeholders of a project by identifying which stakeholders need to be involved, and how they are communicated with?
TheTriple Helix Systemdescribes how added value can be derived from a project through which three factors within the supply chain network?Select THREE
In Project Management, what roles does theBoard/Steering Groupperform?Select TWO