Thecontrol stageensures that resources, people, and materials areavailable when needed, that progress is monitored, and that corrective actions are taken when deviations occur. It focuses on resource flow and issue resolution — not strict adherence to plan, since projects often evolve.
[Reference:CIPS L5M8 Study Guide, p.74., ]