L5M8 Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

Ali is a Project Manager at a large retail organisation within the UK. He has created a project timeline and allocated a budget. However, two months into the project the UK declares a national lockdown due to an unknown virus sweeping the nation. What type of complexity is this known as?


A.

structural complexity


B.

technical complexity


C.

directional complexity


D.

temporal complexity


Get Premium L5M8 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.