Pass the CIMA CIMA Certificate BA2 Questions and answers with CertsForce

Viewing page 4 out of 11 pages
Viewing questions 31-40 out of questions
Questions # 31:

During the completion of Job A, £1,000 worth of material was transferred to it from Job B which had finished ahead of schedule.

How will this be inputted into the Job B account?

Options:

A.

Job A, £1,000 credit


B.

Job A, £1,000 debit


C.

Job B, £1,000 debit


D.

Job B, £1,000 credit


Expert Solution
Questions # 32:

Refer to the exhibit.

Question # 32

Budget information for 'Cast Engineering' is as follows:

The budget cost allowance for an output of 1,300 units is:


Expert Solution
Questions # 33:

A feature of a normal curve is that it is asymptotic, meaning that _______.

Options:

A.

it extends into infinity.


B.

the mean divides the curve exactly in half.


C.

the area under the curve = 1.


Expert Solution
Questions # 34:

JB has fixed costs of $120,000 per annum. It manufactures a single product which it sells for $12 per unit. It has a profit/volume ratio of 60%.

JB’s break-even point is


Expert Solution
Questions # 35:

Refer to the exhibit.

Question # 35

The following standard cost information relates to the production department of Brace Engineering Ltd.

The actual data for the month of March was as follows:

Question # 35

What is the direct labour rate variance (to the nearest whole number)?

Options:

A.

£2,500 favourable


B.

£2,500 adverse


C.

£2,656 favourable


D.

£2,656 adverse


Expert Solution
Questions # 36:

Refer to the exhibit.

Question # 36

The following costs apply to batch 325, which consists of 10000 units of identical products:

The company charges selling and administration costs at a rate of 20% of production costs and wishes to achieve a profit margin of 20% of sales.

What is the required selling price per unit of product?

Give your answer to 2 decimal places.


Expert Solution
Questions # 37:

A company employs 28 production workers for 40 hours per week. The workers are paid $6 per hour during normal time and an overtime premium of 20%. It is anticipated that the employees will work at 95% efficiency.

Budgeted production for next week is 608 units and each unit requires 2 direct labour hours.

What is the direct labour cost budget for the week?

Options:

A.

$7,872


B.

$6,973


C.

$7,411


D.

$7,680


Expert Solution
Questions # 38:

It is company policy that the closing inventory of finished goods must be equal to 10% of the following month's budgeted sales. The budget sales for November and December are 50,000 and 40,000 units respectively.

The budgeted production for November will be


Expert Solution
Questions # 39:

Refer to the exhibit.

Question # 39

Budgeted data for the month of August for product E is given below:

Each unit of E takes 8 labour hours to make and due to stringent quality control standards, 5% of units are rejected after completion.

The direct labour hour budget for the month of August is:


Expert Solution
Questions # 40:

Refer to the exhibit.

Question # 40

A departmental budgetary control report for the latest period includes the following information.

The budgeted variable production cost per unit is

Options:

A.

$10


B.

$12


C.

$16


D.

$17


Expert Solution
Viewing page 4 out of 11 pages
Viewing questions 31-40 out of questions