Questions # 11:

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

Options:

A.

Change the Task Duration Type to Effort Driven


B.

Change the Task Duration Type to Calculated Work


C.

Change the Task Constraint to Fixed Dates


D.

Change the Task Constraint to As Soon As Possible


Expert Solution
Questions # 12:

Which Workfront collection of users allows a task or issue to be assigned to multiple people?

Options:

A.

Team


B.

Group


C.

Project Team


Expert Solution
Questions # 13:

Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?

Options:

A.

USER.NAME


B.

USER.ID


C.

USER.roleID


Expert Solution
Questions # 14:

To whom or what would a project owner assign a task so the task is visible in a Scrum or Kanban backlog?

Options:

A.

A user that has access to a burndown


B.

A job role labeled as Agile User


C.

A team marked as an agile team


Expert Solution
Questions # 15:

A project manager has assigned a task to a team. One of the members of the team wants to volunteer to complete the task.

Where would the volunteer navigate to do this?

Options:

A.

Team Settings > Select Assign to


B.

Team Settings > Work on it


C.

Team Requests > Work on it


D.

Team Requests > Select Assign to


Expert Solution
Questions # 16:

A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to log the risk?

Options:

A.

Log a risk as part of the project business case and identify it as a " schedule " risk.


B.

Log an issue on the project and explain that the completion date is at risk.


C.

Create a task in the project and set the Planned Completion Date for 2 weeks.


Expert Solution
Questions # 17:

Which group of project elements can be used to monitor an active project’s progress?

Options:

A.

Gantt chart, project Condition, and Metrics


B.

Risks, planned hours, and resource utilization


C.

Project status, Updates, and Sharing


Expert Solution
Questions # 18:

A copywriter wants to see his incomplete tasks for projects to which he is assigned.

Which steps should the project manager take to create a custom Workfront report with this information?

Options:

A.

Visit the Reports page, create a new Project report, add filters for Project Status > Equal > Current and Project Owner ID > Equal > [User Name]


B.

Visit the Reports page, create a new Task report, and add the filter Task > Assigned To Role ID > Equal > Copywriter and Task Status > Not Equal > Complete


C.

Visit the Reports page, create a new Task report, add filters for Task Status > Not Equal > Complete and Assignment Users Name > Equal > [User Name]


Expert Solution
Questions # 19:

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

Options:

A.

Visit the Project page and create a new filter. Update the " Pending Approval " filter to " true " and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.


B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the " Pending Approval " filter to " true, " and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.


C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to " tasks " and " issues. " In the grouping tab, add a grouping for project name.


Expert Solution
Questions # 20:

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Options:

A.

Projected Date


B.

Planned Date


C.

Estimated Date


Expert Solution