A copywriter wants to see his incomplete tasks for projects to which he is assigned.
Which steps should the project manager take to create a custom Workfront report with this information?
A.
Visit the Reports page, create a new Project report, add filters for Project Status > Equal > Current and Project Owner ID > Equal > [User Name]
B.
Visit the Reports page, create a new Task report, and add the filter Task > Assigned To Role ID > Equal > Copywriter and Task Status > Not Equal > Complete
C.
Visit the Reports page, create a new Task report, add filters for Task Status > Not Equal > Complete and Assignment Users Name > Equal > [User Name]
To filter tasks that are incomplete and assigned to a specific user, the correct approach is to create a Task report, then filter by Task Status that is " Not Equal " to Complete. Additionally, the Assignment filter should include the user’s name to ensure only tasks assigned to the specified copywriter are shown.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit