Questions # 1:

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

Options:

A.

Queue Details


B.

Project Details


C.

Metrics


Expert Solution
Questions # 2:

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

Options:

A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.


B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.


C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.


Expert Solution
Questions # 3:

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

Options:

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.


B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.


C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.


D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.


Expert Solution
Questions # 4:

Which two options are available with Workfront reports? (Choose two.)

Options:

A.

A chart report that references a multi-select custom field


B.

Planned date-based calendar reports


C.

Filters with a custom grouping


D.

An object name with more than 500 characters


Expert Solution
Questions # 5:

A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?

Options:

A.

Business Case


B.

Billing Records


C.

Project Details


Expert Solution
Questions # 6:

A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

Options:

A.

Convert the issue into a project using a project template.


B.

Email the management team and request their approval.


C.

Use a customized approval process to route the issue for approval.


Expert Solution
Questions # 7:

Question # 7

What do the connector lines between tasks in a Gantt chart represent?

Options:

A.

Critical path


B.

Multiple assignments


C.

Predecessor relationship


Expert Solution
Questions # 8:

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:

A.

Set the task condition to At Risk.


B.

Update the Commit Date on the task.


C.

Work on the task and complete it in the given duration.


Expert Solution
Questions # 9:

The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.

Which report grants the executive team this visibility?

Options:

A.

A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.


B.

A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.


C.

A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.


Expert Solution
Questions # 10:

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

Options:

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.


B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."


C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."


Expert Solution