AD0-E903 Exam Topic 1 Question 29 Discussion:
Question #: 29
Topic #: 1

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?


A.

Set the task condition to At Risk.


B.

Update the Commit Date on the task.


C.

Work on the task and complete it in the given duration.