Question #: 23
Topic #: 1

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?


A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.


B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.


C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.