Questions # 31:

If a project is said to be on a "fast track program/' the fast track method is:

Options:

A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work


B.

First completing engineering and procurement, then executing construction


C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance


D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime


Expert Solution
Questions # 32:

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following is least likely to improve a large earthmoving contractor's productivity?

Options:

A.

Using apprentice operators to save labor costs


B.

Starting summer work in the early morning hours to minimize work during peak heat periods of the day


C.

Remove underground hazards prior to excavation work


D.

Replacing old excavators with new, larger excavators


Expert Solution
Questions # 33:

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Costs which are independent of the system throughout are:

Options:

A.

no answers ate correct


B.

both fixed and variable costs


C.

variable costs fixed costs


D.

fixed costs


Expert Solution
Questions # 34:

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

You have been asked to provide ETC information to management. Based on the following information, what is the ETC?

Original Budget = $9,000,000

Actuals to date = $3,513,000

Current estimate at completion = $10,613,000

Actuals for current month = $1,200,000

Options:

A.

$10,613,000


B.

$9,000,000


C.

$5,487,000


D.

$7,100,000


Expert Solution
Questions # 35:

Develop a CPM method considering the below tasks and logical relationships. Use this information to answer the related questions.

Question # 35

What is the late finish date of activity 50?

Options:

A.

Day 47


B.

Day 38


C.

Day 28


D.

Day 37


Expert Solution
Questions # 36:

The process of stating goals and determining the most effective way of reaching them is the definition for:

Options:

A.

Implementing


B.

Mission Statement


C.

Managing


D.

Planning


Expert Solution
Questions # 37:

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Why is a +/- notation necessary when developing an estimate?

Options:

A.

Contingency cushion


B.

It makes up for the lack of time to develop a real estimate


C.

It is a government requirement


D.

There are unknowns that affect the final cost of a project


Expert Solution
Questions # 38:

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

Question # 38

Marketing has determined that XY2 can safely increase their per unit selling price to SO.55. The new break even amount for sales (in units) based on the new contribution margin is:

Options:

A.

40,000 units


B.

6,000 units


C.

50,000 units


D.

60,000 units


Expert Solution
Questions # 39:

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

Options:

A.

82%


B.

75%


C.

90%


D.

84%


Expert Solution
Questions # 40:

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

Question # 40

If the fixed rent remains unchanged, and XYZ pays S0.01 per unit as additional rent, the monthly breakeven point in numbers of units becomes:

Options:

A.

48,500 units


B.

66,667 units


C.

52,500 units


D.

33,333 units


Expert Solution