Pass the AACE International AACE Certification CCP Questions and answers with CertsForce

Viewing page 5 out of 6 pages
Viewing questions 41-50 out of questions
Questions # 41:

The four steps to writing are:

Options:

A.

Introduction, paragraph, conclusion, works cited


B.

Start, write, complete, revise


C.

Abstract, body conclusion, bibliography


D.

Plan, write, cool, revise


Expert Solution
Questions # 42:

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

Question # 42

The following question requires your selection el Scenario 1.4.150 from the right side of your split screen. using the drop down menu to reference during your response/choice of responses.

Based on your analysis, should the press be purchased?

Options:

A.

CR is not a factor in this decision


B.

Not enough data to determine


C.

No


D.

Yes


Expert Solution
Questions # 43:

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

How does the project stand?

Options:

A.

Schedule is good, cost is bad


B.

Schedule is good cost is good


C.

Schedule is bad cost is good


D.

Schedule is bad, cost is bad


Expert Solution
Questions # 44:

Question # 44

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?

Options:

A.

6,600


B.

6,960


C.

7,200


D.

6,573


Expert Solution
Questions # 45:

Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:

Options:

A.

Activity ID


B.

WBS Code


C.

Resource


D.

Account number


Expert Solution
Questions # 46:

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

Question # 46

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses

What is the amount of capital recovery with salvage?

Options:

A.

$11,499.00


B.

$4,124.00


C.

$9,876.00


D.

$10,765.00


Expert Solution
Questions # 47:

Budgeted cost of work scheduled is all of the following except:

Options:

A.

Total costs incurred in accomplishing work in a given-time period


B.

Baseline for performance measurement


C.

Sum of the budgets for work scheduled


D.

Includes portion of the budget for level-of-effort work


Expert Solution
Questions # 48:

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the schedule variance (SV)?

Options:

A.

BCWS - BCWP = 100.000 – 105,000 = -5,000


B.

ACWP - BCWS = 110.000 – 100,000 = 10,000


C.

BCWS -ACWP = 100.000 – 110,000 - -10,000


D.

BCWP - BCWS = 105.000 - 100.000 =- 5,000


Expert Solution
Questions # 49:

____________is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts.

Options:

A.

Percent complete


B.

Cost to complete


C.

Earned value


D.

Forecast


Expert Solution
Questions # 50:

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

Options:

A.

ACWP/BCWS


B.

BCWS/BCWP


C.

ACWP/BCWP


D.

BCWP/ACWP


Expert Solution
Viewing page 5 out of 6 pages
Viewing questions 41-50 out of questions