AACE International Certified Cost Professional (CCP) Exam CCP Question # 43 Topic 5 Discussion

AACE International Certified Cost Professional (CCP) Exam CCP Question # 43 Topic 5 Discussion

CCP Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

How does the project stand?


A.

Schedule is good, cost is bad


B.

Schedule is good cost is good


C.

Schedule is bad cost is good


D.

Schedule is bad, cost is bad