AACE International Certified Cost Professional (CCP) Exam CCP Question # 31 Topic 4 Discussion

AACE International Certified Cost Professional (CCP) Exam CCP Question # 31 Topic 4 Discussion

CCP Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

If a project is said to be on a "fast track program/' the fast track method is:


A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work


B.

First completing engineering and procurement, then executing construction


C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance


D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime