AACE International Certified Cost Professional (CCP) Exam CCP Question # 32 Topic 4 Discussion

AACE International Certified Cost Professional (CCP) Exam CCP Question # 32 Topic 4 Discussion

CCP Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following is least likely to improve a large earthmoving contractor's productivity?


A.

Using apprentice operators to save labor costs


B.

Starting summer work in the early morning hours to minimize work during peak heat periods of the day


C.

Remove underground hazards prior to excavation work


D.

Replacing old excavators with new, larger excavators


Get Premium CCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.