Questions # 11:

Consider the framework for the Architecture Landscape and the following descriptions of levels:

    Direction setting at an executive level.

    Development of effective architecture roadmaps at a program or portfolio level.

Match the levels marked A, B, or C to the descriptions marked 1 and 2.

Options:

A.

A. B–1, C–2


B.

B. B–2, C–1


C.

C. A–2, B–1


D.

D. A–1, C–2


Expert Solution
Questions # 12:

Which of the following best summarizes the purpose of Enterprise Architecture?

Options:

A.

Taking major improvement decisions.


B.

Guiding effective change.


C.

Controlling the bigger changes.


D.

Governing the Stakeholders.


Expert Solution
Questions # 13:

What ensures that a project transitioning into implementation also smoothly transitions into appropriate Architecture Governance?

Options:

A.

Implementation Strategy


B.

Implementation Governance Model


C.

Transition Plan


D.

Migration Plan


Expert Solution
Questions # 14:

Complete the sentence. The four purposes that typically frame the planning horizon, depth and breadth of an Architecture Project, and the contents of the EA Repository are Strategy, Portfolio,

Options:

A.

Project, and Solution Delivery.


B.

Subordinate, and Superior Architecture.


C.

Discreet, and Cohesive.


D.

Segment, and End-to-end Target Architecture.


Expert Solution
Questions # 15:

Consider the following statements:

1. Each contracted party is required to act responsibly to the organization and its stakeholders.

2. All decisions taken, processes used, and their implementation will not be allowed to create unfair advantage to any one particular party.

3. Digital Transformation and operations will be more effective and efficient.

4. Strategic decision-making by C-Level executives and business leaders will be more effective.

Which statements highlight the value and necessity for Architecture Governance to be adopted within organizations?

Options:

A.

1 & 2


B.

2 & 3


C.

3 & 4


D.

1 & 4


Expert Solution
Questions # 16:

In the ADM, what is the name for documents that are not finished and not approved?

Options:

A.

interim


B.

draft


C.

version 0.1


D.

incomplete


Expert Solution
Questions # 17:

Consider the illustration.

Question # 17

What are the items labelled A, B and C?

Options:

A.

A-Enterprise Continuum, B-Architecture Continuum, C-Solutions Continuum


B.

A-Enterprise Architecture, B-Architecture Building Blocks, C-Solutions Building Blocks


C.

A-Architecture Vision, B-Business Architecture, C-Information Systems Architecture


D.

A-Enterprise Strategic Architecture, B-Segment Architecture, C-Solutions Architecture


Expert Solution
Questions # 18:

Complete the sentence. The key purpose of Gap Analysis is to _____

Options:

A.

establish quality parameters for the architecture


B.

identify potential missing or overlapping functions


C.

validate nonfunctional requirements


D.

identify commercial building blocks to be purchased


E.

determine the required service levels for the architecture


Expert Solution
Questions # 19:

What is the purpose of the Preliminary Phase?

Options:

A.

Developing an Enterprise Architecture Capability.


B.

Describing the target architecture.


C.

Defining the Enterprise Strategy.


D.

Identifying the stakeholders and their requirements.


Expert Solution
Questions # 20:

What is an objective of the ADM Implementation Governance Phase?

Options:

A.

To provide continual monitoring of the governance framework


B.

To ensure conformance for the target architecture


C.

To finalize the Implementation and Migration Plan


D.

To establish the resources for architecture governance


Expert Solution
Viewing page 2 out of 4 pages