Developers are self-managing, which of the following do they manage?
(choose the best answer)
A new Developer is having continuing conflicts with existing members of the Scrum Team,
which is impacting the delivery of the Increment. If necessary, who is responsible for removing
the Developer from the Scrum Team?
(choose the best answer)
What may be included in the Sprint Backlog?
(choose the best answer)
What are the two responsibilities of testers in a Scrum Team?
(choose the best two answers)
The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should:
(choose the best answer)
Which of the following are the Developers accountable for?
(choose the best two answers)
How much of the Sprint Backlog must be defined during the Sprint Planning event?
(choose the best answer)
Which are characteristics of the Daily Scrum?
(choose the best two answers)
What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of
productivity?
(choose the best two answers)
Who can cancel a Sprint?
(choose the best answer)