Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 21 Topic 3 Discussion

Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 21 Topic 3 Discussion

PSPO-I Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

Developers are self-managing, which of the following do they manage?

(choose the best answer)


A.

Product Backlog ordering.


B.

When to release, based on its progress.


C.

Sprint Backlog.


D.

Stakeholders for the Sprint Review.


E.

Sprint length.


Get Premium PSPO-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.