Questions # 41:

When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?

(choose the best answer)

Options:

A.

Whenever a team member can accommodate more work.


B.

At the Sprint Planning Event.


C.

During the Daily Scrum.


D.

Never. The entire Scrum Team is accountable for creating value every Sprint.


Expert Solution
Questions # 42:

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.

(choose the best two answers)

Options:

A.

Each Scrum Team should have a separate Product Backlog.


B.

There should be only one Product Owner.


C.

The product has one Product Backlog.


D.

There should be six Product Owners, one for each Scrum Team.


E.

There should be six Product Owners, reporting to a Chief Product Owner.


Expert Solution
Questions # 43:

Who determines how work is performed during the Sprint?

(choose the best answer)

Options:

A.

The Scrum Master.


B.

The Scrum Team.


C.

Team manager.


D.

The Developers


E.

Subject matter experts.


Expert Solution
Questions # 44:

A Scrum Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what done means.

(choose the best two answers)

Options:

A.

No work is left to meet the Definition of Done.


B.

Whatever the Product Owner defines as quality.


C.

Ready for integration.


D.

Ready to be released to end users.


E.

All work the Developers are willing to do.


Expert Solution
Questions # 45:

What is the accountability of the Product Owner during Sprint 0?

(choose the best answer)

Options:

A.

Determine the composition of the Scrum Team to meet the release plan.


B.

There is no such thing as Sprint 0.


C.

Create the overall release plan to ensure that organizational goals are met.


D.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.


E.

Gathering, eliciting, and analyzing the requirements to build the Product Backlog.


Expert Solution
Questions # 46:

Which statement best describes a Product Owner's responsibility?

(choose the best answer)

Options:

A.

Ensuring that the work meets the commitments to the stakeholders.


B.

Maximizing the value of the work the Scrum Team does.


C.

Keep stakeholders from distracting the Developers.


D.

Directing the Developers.


Expert Solution
Questions # 47:

The Scrum Team should have all the skills needed to:

(choose the best answer)

Options:

A.

Complete the project within the date and cost as calculated by the Product Owner.


B.

Do all of the development work, except for specialized testing that requires additional

tools and environments.


C.

Turn Product Backlog items into a valuable, useful Increment.


Expert Solution
Questions # 48:

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)

Options:

A.

Add them to the Product Backlog to ensure transparency.


B.

Run the integration and regression tests before the end of the Sprint, and

capture the open work for the Sprint Backlog of the next Sprint.


C.

Add them to the Definition of Done so the work is taken care of every Sprint.


D.

Put them on a separate list on the Scrum board, available for all to see.


Expert Solution
Questions # 49:

What enhances the transparency of an Increment?

(choose the best answer)

Options:

A.

Keeping track of and estimating all undone work to be completed in a "hardening"

Sprint.


B.

Doing all work needed to meet the Definition of Done.


C.

Reporting Sprint progress to the stakeholders daily.


D.

Updating Sprint tasks properly in the electronic tracking tool.


Expert Solution
Questions # 50:

Which topics should be discussed in the Sprint Review?

(choose the best answer)

Options:

A.

The Scrum process, and how it was used during the Sprint.


B.

Coding and engineering practices.


C.

The product Increment.


D.

All of the above.


Expert Solution