Questions # 31:

(Select 2) Why is Architectural Runway important?

Options:

A.

It supports a stable velocity.


B.

It provides the documentation on which Features and Capabilities are built.


C.

It iteratively evolves the architecture to meet changing needs.


D.

It allows for nontechnical changes


Expert Solution
Questions # 32:

Capabilities are similar to Features and can be managed in the Program Backlog.

Options:

A.

True


B.

False


Expert Solution
Questions # 33:

A company is about to launch Agile Release Trains within a Value Stream that consists of 200 people, 90 of whom are in the U.S. working on the system's business logic and databases, and 110 of whom are in India working on the UI front end.

What would be the most effective way to launch?

Options:

A.

Launch it as two or more ARTs based on how the cost centers are defined.


B.

Launch it as two distributed ARTs organized around end-to-end functionality.


C.

Launch it as two geography-based ARTs, with one working on the UI and the other on business logic and databases.


D.

Launch it as a single ART and then conduct Inspect & Adapt at the end of the PI to determine whether it needs to be split.


Expert Solution
Questions # 34:

(Select 2) What are the responsibilities of a Business Owner?

Options:

A.

Assign business value to Team Objectives during PI Planning.


B.

Participate in Post-PI Planning and assist trains in adjusting ART PI plans as needed.


C.

Assign business value to Epics and Features.


D.

Ensure that the Solution Demo occurs.


E.

Determine the product Roadmap


Expert Solution
Questions # 35:

(Select 3) According to Lean thinking, how is fast and sustainable flow achieved?

Options:

A.

By understanding the full Value Stream.


B.

By constant reduction of delays.


C.

By reducing batch sizes.


D.

By applying subjective governance.


Expert Solution
Questions # 36:

(Select 3) What are the primary reasons to limit WIP?

Options:

A.

Reduce multiplexing


B.

Decrease wait times


C.

Expand context switching


D.

Make it easier to visualize the important work


E.

Increase throughput


Expert Solution
Questions # 37:

Your organization decided to thoroughly implement the SAFe Principle "Assume variability; preserve options." What is the optimum path for success?

Options:

A.

Assume variability of scope and preserve options for the release date.


B.

Preserve flexibility in system functionality and design, but have fixed Solution intent.


C.

Assume variability of scope, but have fixed Solution Context.


D.

Preserve flexibility in both system functionality and design.


Expert Solution
Questions # 38:

(Select 2) What are the right scenarios for using SAFe Foundations Training Materials?

Options:

A.

Train Scrum Masters in servant leadership following "SAFe for Teams" training.


B.

Make an initial presentation on SAFe to the organization.


C.

Familiarize Release Train Engineers with the PI Planning process.


D.

Familiarize executives with SAFe.


E.

Train the teams prior to PI Planning.


Expert Solution
Questions # 39:

What contributes to establishing trust in SAFe?

Options:

A.

Decentralization of control.


B.

Transparency.


C.

Reporting.


D.

U-curve optimization.


E.

Servant leadership.


Expert Solution
Questions # 40:

(Select 2) What would you examine when identifying Value Streams in an enterprise moving to SAFe?

Options:

A.

The project cost accounting procedures in place.


B.

The internal departments which are supported.


C.

The number of ARTs which would be contained in the Portfolio.


D.

The current products which the company sells.


Expert Solution