Questions # 61:

During which part of an Inspect and Adapt event would differences between planned business value and actual business value be presented?

Options:

A.

Retrospective


B.

Problem-solving workshop


C.

Quantitative and qualitative measurement


D.

PI system demo


Expert Solution
Questions # 62:

Which one SAFe core value creates an environment where facts are always friendly?

Options:

A.

Transparency


B.

Respect for People and Culture


C.

Flow


D.

Innovation


Expert Solution
Questions # 63:

During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the man-agement team help ensure they complete the Feature within the PI?

Options:

A.

Use buffer resources as a guard band


B.

Redefine the definition of done for Features


C.

ROAM the risk appropriately


D.

Negotiate a reduction in scope of the Feature


Expert Solution
Questions # 64:

Why is a confidence vote held at the end of program increment (Pl) planning?

Options:

A.

To build shared commitment to the plan


B.

To remove the risks for the Pl


C.

To ensure the business owners accept the plan


D.

To hold the teams accountable if the Agile release train (ART) does not deliver on its commitment


Expert Solution
Questions # 65:

The Release Train Engineer (RTE) learns the teams feel the business value does not re-flect the effort and progress. What are two ways the RTE can provide a better under-standing of what the teams have created? (Choose two.)

Options:

A.

Educate teams that business value provides the Enterprise with a Metric of how fast the team executed work during the PI


B.

Coach the Business Owner's review of objectives to see that scoring is against the specific details negotiated with the team during PI Planning


C.

Illustrate the linkage between business values and the market communica-tions/release objectives tied to the three to six month Enterprise strategy


D.

Work with the team to ensure they are actively involved when the Business Own-ers score the business value achieved

Publish the team business values and coach teams that these values are for track-ing each Agile Release Train deliverable


Expert Solution
Questions # 66:

What are two benefits of having a team definition of done? (Choose two.)

Options:

A.

To measure the team's capacity to load ratio


B.

To increase predictability


C.

To collect team performance metrics


D.

To improve quality


E.

To gauge team predictability


Expert Solution
Questions # 67:

What is one primary responsibility of a Release Train Engineer?

Options:

A.

Eliminate impediments


B.

Support the Product Owner


C.

Manage and optimize the Release on Demand process


D.

Manage and optimize the flow of value through the Agile Release Train


Expert Solution