Scaled Agile SAFe Release Train Engineer (RTE 6.0) SAFe-RTE Question # 64 Topic 7 Discussion

Scaled Agile SAFe Release Train Engineer (RTE 6.0) SAFe-RTE Question # 64 Topic 7 Discussion

SAFe-RTE Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

Why is a confidence vote held at the end of program increment (Pl) planning?


A.

To build shared commitment to the plan


B.

To remove the risks for the Pl


C.

To ensure the business owners accept the plan


D.

To hold the teams accountable if the Agile release train (ART) does not deliver on its commitment