Questions # 1:

Project structure.

You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

Options:

A.

You can create project coding mask X... event if there are project numbers beginning with X.


B.

The standard project definition must differ from the definition of the operative project.


C.

You can use only numbers for a project coding mask definition.


D.

You can use an indicator to determine that only coded project numbers may be used within the project system.


Questions # 2:

Which organizational structures are required for network activities? Note: There are 3 correct answers to this question

Options:

A.

Controlling area


B.

Plant


C.

Sales organization


D.

Company code


E.

Operating concern


Questions # 3:

Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question

Options:

A.

Basic dates


B.

Forecast dates


C.

Baseline dates


D.

Planned dates


Questions # 4:

You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?

Options:

A.

Missing budget for material components


B.

Missing reservations for material components


C.

Missing material availability


D.

Missing authorizations to release material components


Questions # 5:

Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

Options:

A.

Project versions can be changed


B.

Project versions are mandatory for Milestone Trend Analysis (MTA)


C.

Project versions can be created automatically based on user status


D.

Manually Created project versions always require a project version profile


Questions # 6:

COST AND BUDGET

You have assigned a budget to WBS element with your project

What budget function could be used to check assigned values against the current budget?

Options:

A.

Easy cost planning


B.

Results analysis


C.

Cost forecast


D.

Availability control


Questions # 7:

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

Options:

A.

Enter an offset of -18 days to the finish date of the activity


B.

Enter February 10 as fixed date


C.

Enter 10 days as duration


D.

Enter an offset of 10 days to the start date of the activity


Questions # 8:

To which object can you assign a factory calendar?

Options:

A.

Material component


B.

Network header


C.

Relationship


D.

Milestone


Questions # 9:

The various work packages in the project are described as individual______________. Choose the correct answer.

Options:

A.

WBS elements


B.

Project definitions


C.

Tasks


D.

Activities


Questions # 10:

For which objects can billing plans be created? Note: There are 2 correct answers to this question

Options:

A.

WBS elements


B.

Project definition


C.

Sales order items


D.

Milestones