Questions # 31:

Where do you maintain the length of the project ID?

Options:

A.

Special characters


B.

Project coding mask


C.

Project profile


D.

Project type


Questions # 32:

In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

Options:

A.

The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)


B.

The purchase order is updated automatically to match the new quantity while saving the project.


C.

A workflow can be triggered to inform the purchasing group.


D.

The system automatically creates a new purchase requisition with the difference to the original quantity


Questions # 33:

A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

Options:

A.

The network activity is assigned to a WBS element


B.

The network is assigned to a sales order item


C.

The material master of the component must permit project stock management


D.

The Project Stock indicator is set in the project definition (non-valuated or valuated)


E.

A procurement indicator must be assigned to the activity