SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 33 Topic 4 Discussion

SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 33 Topic 4 Discussion

C_TS412_2021 Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question


A.

The network activity is assigned to a WBS element


B.

The network is assigned to a sales order item


C.

The material master of the component must permit project stock management


D.

The Project Stock indicator is set in the project definition (non-valuated or valuated)


E.

A procurement indicator must be assigned to the activity


Get Premium C_TS412_2021 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.