SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 33 Topic 4 Discussion
C_TS412_2021 Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
A.
The network activity is assigned to a WBS element
B.
The network is assigned to a sales order item
C.
The material master of the component must permit project stock management
D.
The Project Stock indicator is set in the project definition (non-valuated or valuated)
E.
A procurement indicator must be assigned to the activity
To generate project stock reservations for a component assigned to a network activity, the following prerequisites must be met:
The network activity must be assigned to a WBS element that is relevant for project stock management.
The material master of the component must have a procurement type that allows project stock management (such as E, F, or X) and an individual/collective requirements indicator that allows individual requirements (such as 2 or 4).
The project definition must have the Project Stock indicator set to either non-valuated or valuated project stock. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html? &version=1909.002