You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
How can you grant individual authorization for WBS elements and networks?
The__________________that you specify when you create a project definition is unique for theentire project. Choose the correct answer.
A service company uses project management and they complain that the system does not prevent
their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
Dates
How are earliest dates and latest dates of activities schedule?
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
What are the prerequisites for resource-related billing? Note: There are 2 correct answers to this question
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?