Questions # 21:

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

Options:

A.

You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"


B.

You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"


C.

You can always maintain the actual start and finish date of a WBS element


D.

You can only maintain the actual start of a WBS element if the finish date is not maintained


Questions # 22:

Material

How can the system activate requirements (such as reservations or purchase requisitions)?

Note: There are 2 correct answers to this question

Options:

A.

Immediately, by saving the project


B.

Automatically, using the requirement date and the replenishment lead time


C.

Using a standard milestone activity


D.

When releasing a network or an activity


Questions # 23:

How can you grant individual authorization for WBS elements and networks?

Options:

A.

Define a user status to lock the business transaction Update Project.


B.

Set the system status to "Lock Master Data".


C.

Activate access control lists (ACL) for the user master record.


D.

Activate access control lists (ACL) for the project profile and the network profile


Questions # 24:

The__________________that you specify when you create a project definition is unique for theentire project. Choose the correct answer.

Options:

A.

Plant


B.

Controlling area


C.

Company code


D.

Planning department


Questions # 25:

A service company uses project management and they complain that the system does not prevent

their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

Options:

A.

Activate availability control for the WBS elements. Define the tolerance limits on each WBS element


B.

Activate availability control in the assigned budget profile. Define the tolerance limits in customizing


C.

Activate commitment management in the project definition Enter the budget in the master data of the top WBS element


D.

Activate availability control for projects in the controlling area. Enter the plan data for each WBS element


Questions # 26:

Dates

How are earliest dates and latest dates of activities schedule?

Options:

A.

Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.


B.

Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.


C.

Earliest dates and latest dates are scheduled by forward scheduling.


D.

Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.


Questions # 27:

Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

Options:

A.

Individual overview capacity requirements


B.

Capacity load work center view


C.

Extended capacity evaluation


D.

Structure overview


Questions # 28:

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

Options:

A.

Material master


B.

Network activity


C.

WBS element


D.

BOM item


Questions # 29:

What are the prerequisites for resource-related billing? Note: There are 2 correct answers to this question

Options:

A.

A dynamic item processor (DIP) profile with the appropriate settings


B.

Released WBS elements, activities, and/or activity elements


C.

A header-account-assigned network that is assigned to a sales order item


D.

An activity-account-assigned network that is assigned to a sales order item


Questions # 30:

You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

Options:

A.

Activity


B.

Network header


C.

Milestone


D.

Activity element