SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 21 Topic 3 Discussion

SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 21 Topic 3 Discussion

C_TS412_2021 Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question


A.

You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"


B.

You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"


C.

You can always maintain the actual start and finish date of a WBS element


D.

You can only maintain the actual start of a WBS element if the finish date is not maintained


Get Premium C_TS412_2021 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.