SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 21 Topic 3 Discussion
C_TS412_2021 Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
A.
You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
B.
You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
C.
You can always maintain the actual start and finish date of a WBS element
D.
You can only maintain the actual start of a WBS element if the finish date is not maintained
If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status “Released” or “Partially released”, which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html