An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
To control whether the delivery date for an external component assigned to a network activity is defined by the earliest or latest scheduled dates, you can use the scheduling parameters for the network. An external component is a material component that is required for executing a network activity and that is procured externally from vendors or other plants