SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 28 Topic 3 Discussion
C_TS412_2021 Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
To enable automatic assignment of material components to the project, you have to maintain the material master and the BOM item. The material master contains the data required for planning and procurement of materials. The BOM item contains the data required for assigning materials to a network activity or a WBS element. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html