Pass the SAP SAP Certified Application Associate C_TPLM22_67 Questions and answers with CertsForce

Viewing page 4 out of 5 pages
Viewing questions 31-40 out of questions
Questions # 31:

Which type of reports allows you to choose the objects whose costs you want to analyze or call up an appropriate list and choose the period you want to evaluate?

Please choose the correct answer.

Response:

Options:

A.

Hierarchy reports


B.

Cost element reports


C.

Period analysis reports


D.

Structural reports


Expert Solution
Questions # 32:

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?

There are 3 correct answers to this question.

Response:

Options:

A.

Scheduling must have been carried


B.

A distribution key must be maintained in the work center


C.

A work center must be maintained in the activity


D.

The capacity requirements indicator must not be set in the network header


Expert Solution
Questions # 33:

Which of the following levels can you assign persons to work centers?

There are 2 correct answers to this question.

Response:

Options:

A.

Workforce planning level


B.

Assignment level


C.

Capacity category level


D.

Work center level


Expert Solution
Questions # 34:

Which of the following can be derived automatically when you carry out scheduling in projects with networks?

There are 2 correct answers to this question.

Response:

Options:

A.

Activity dates


B.

WBS element dates


C.

Network dates


D.

Scheduling dates


Expert Solution
Questions # 35:

Which combination allows you to assign the material components in one WBS element to different grouping WBS element?

There are 2 correct answers to this question.

Response:

Options:

A.

Plant


B.

Material group


C.

MRP group


D.

WBS group


Expert Solution
Questions # 36:

How do you create a detailed payment schedule if the expense for an external activity or purchased component is not paid with a single invoice?

Please choose the correct answer.

Response:

Options:

A.

Invoicing plan


B.

Billing plan


C.

Credit memos


D.

Detailed billing plan


Expert Solution
Questions # 37:

Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?

There are 3 correct answers to this question.

Response:

Options:

A.

Scheduling of subnetworks and subordinate internal orders


B.

Introduction of a configurable level concept for the targeted selection of


C.

Scheduling that takes available capacities and material availability into


D.

Improve performance through the targeted selection of subnetworks to be


E.

Detailed subnetwork monitor


Expert Solution
Questions # 38:

In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?

Please choose the correct answer.

Response:

Options:

A.

Periodic settlement


B.

Full settlement


C.

Profile settlement


D.

Overview settlement


Expert Solution
Questions # 39:

How does a project manager plan resources in cProjects and define responsibilities for different objects?

There are 2 correct answers to this question.

Response:

Options:

A.

Users


B.

Alerts


C.

Roles


D.

Business partners


Expert Solution
Questions # 40:

What are the components on which reporting is based upon, in profit center accounting?

There are 2 correct answers to this question.

Response:

Options:

A.

Cost centers


B.

Cost elements


C.

Profit centers


D.

Profit center hierarchy


Expert Solution
Viewing page 4 out of 5 pages
Viewing questions 31-40 out of questions