SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 37 Topic 4 Discussion
C_TPLM22_67 Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4
Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
There are 3 correct answers to this question.
Response:
A.
Scheduling of subnetworks and subordinate internal orders
B.
Introduction of a configurable level concept for the targeted selection of
C.
Scheduling that takes available capacities and material availability into
D.
Improve performance through the targeted selection of subnetworks to be
Chosen Answer: