Questions # 1:

Which types of networks store all the activity and material component costs at the network header level and behave in the same way as all other order categories?

Please choose the correct answer.

Response:

Options:

A.

Order header networks


B.

Order category networks


C.

Assignment networks


D.

Header assigned networks


Expert Solution
Questions # 2:

Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile?

Please choose the correct answer.

Response:

Options:

A.

Proj.summ.master data indicator


B.

Project summarization indicator


C.

Capacity requirement indicator


D.

Version profile indicator


Expert Solution
Questions # 3:

How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement or fully responsible for procurement?

Please choose the correct answer.

Response:

Options:

A.

Requirements controlling


B.

Requirements grouping


C.

WBS grouping


D.

Project grouping


Expert Solution
Questions # 4:

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?

Please choose the correct answer.

Response:

Options:

A.

Internally-processed activities


B.

Externally-processed activities


C.

Service activities


D.

Scheduled activities


Expert Solution
Questions # 5:

Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?

Please choose the correct answer.

Response:

Options:

A.

Costing variant


B.

Valuation variant


C.

Planned cost variant


D.

Network variant


Expert Solution
Questions # 6:

In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?

There are 2 correct answers to this question.

Response:

Options:

A.

Project view


B.

Resource view


C.

Work center view


D.

Assignment view


Expert Solution
Questions # 7:

What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?

Please choose the correct answer.

Response:

Options:

A.

Workflow indicator


B.

Workflow purchase order change indicator


C.

Workflow change indicator


D.

Purchase order change indicator


Expert Solution
Questions # 8:

All the currency-dependent data in the Project System is managed in three different currencies in parallel. These are;

There are 3 correct answers to this question.

Response:

Options:

A.

Business Area Currency


B.

Controlling area currency


C.

Object Currency


D.

Transaction currency


Expert Solution
Questions # 9:

Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?

Please choose the correct answer.

Response:

Capacity planning board

Options:

A.

Work center planning board


B.

Project planning board


C.

Workforce planning board


Expert Solution
Questions # 10:

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?

Please choose the correct answer.

Response:

Options:

A.

Internally-processed activities


B.

Externally-processed activities


C.

Service activities


D.

Scheduled activities