SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 10 Topic 2 Discussion

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 10 Topic 2 Discussion

C_TPLM22_67 Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?

Please choose the correct answer.

Response:


A.

Internally-processed activities


B.

Externally-processed activities


C.

Service activities


D.

Scheduled activities


Get Premium C_TPLM22_67 Questions

Contribute your Thoughts:


Chosen Answer: