How can the capacity requirements of an activity be reduced?

There are 3 correct answers to this question.

Response:


A.

With partial confirmations of the activity


B.

By transferring the working times for the activity that was entered in CATS (Cross-Application Time Sheet)


C.

With the period-end closing


D.

By setting the status locked account assignment


E.

With the final confirmation of the activity