How can the capacity requirements of an activity be reduced?
There are 3 correct answers to this question.
Response:
With partial confirmations of the activity
By transferring the working times for the activity that was entered in CATS (Cross-Application Time Sheet)
With the period-end closing
By setting the status locked account assignment
With the final confirmation of the activity