SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 32 Topic 4 Discussion

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 32 Topic 4 Discussion

C_TPLM22_67 Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?

There are 3 correct answers to this question.

Response:


A.

Scheduling must have been carried


B.

A distribution key must be maintained in the work center


C.

A work center must be maintained in the activity


D.

The capacity requirements indicator must not be set in the network header


Get Premium C_TPLM22_67 Questions

Contribute your Thoughts:


Chosen Answer: