Which of the following activities is NOT an action of preparing for planned closure?
Which of the following statements is FALSE regarding the Continued Business Justification?
The Calendar project was delivered as originally planned, and Is now preparing for planned closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Which of the following management products ARE updated as part of Managing a stage boundary?
1. Business Case
2. Benefits Review Plan
3. Configuration Item Records
4. Project Brief
BUSINESS CASE
Here are three statements from the business case for the Health and Safety Project.
Under which heading in the business case (A-F) should they be recorded?
Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.

PLANS
During the initiation stage, the project manager is creating the project plan.
Here are three activities carried out as part of PRINCE2’s recommended approach to planning.
As part of which step of the approach (A-F) should each activity be carried out?
Choose only one step for each activity. Each step can be used once, more than once, or not at all.

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?