Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Pass the PRINCE2 PRINCE2 Certification Prince2-Practitioner Questions and answers with CertsForce

Viewing page 8 out of 8 pages
Viewing questions 71-80 out of questions
Questions # 71:

Which of the following activities is NOT an action of preparing for planned closure?

Options:

A.

Update the project plan with actual


B.

Update the Project Management Team


C.

Request a product status account


D.

Confirm project has delivered what is defined in Project Product Description


Expert Solution
Questions # 72:

Which of the following statements is FALSE regarding the Continued Business Justification?

Options:

A.

The justification for the project must remain the same throughout the project.


B.

The justification for the project should remain vabd.


C.

The justification for the project may change.


D.

If the project is no longer justified it should be stopped.


Expert Solution
Questions # 73:

The Calendar project was delivered as originally planned, and Is now preparing for planned closure.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Question # 73


Expert Solution
Questions # 74:

Which of the following management products ARE updated as part of Managing a stage boundary?

1. Business Case

2. Benefits Review Plan

3. Configuration Item Records

4. Project Brief

Options:

A.

1, 2, 3


B.

1, 3, 4


C.

1, 2, 4


D.

2, 3, 4


Expert Solution
Questions # 75:

BUSINESS CASE

Here are three statements from the business case for the Health and Safety Project.

Under which heading in the business case (A-F) should they be recorded?

Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.

Question # 75


Expert Solution
Questions # 76:

PLANS

During the initiation stage, the project manager is creating the project plan.

Here are three activities carried out as part of PRINCE2’s recommended approach to planning.

As part of which step of the approach (A-F) should each activity be carried out?

Choose only one step for each activity. Each step can be used once, more than once, or not at all.

Question # 76


Expert Solution
Questions # 77:

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

Options:

A.

Scope, People & Resources, Benefit


B.

Scope, Risk, Product


C.

Risk, Benefit, Product


D.

Scope, Risk, Benefit


Expert Solution
Viewing page 8 out of 8 pages
Viewing questions 71-80 out of questions