Pass the PRINCE2 PRINCE2 Certification Prince2-Practitioner Questions and answers with CertsForce

Viewing page 1 out of 8 pages
Viewing questions 1-10 out of questions
Questions # 1:

When updating the project plan as part of Managing a stage boundary, what else might be updated?

Options:

A.

Exception Plan


B.

Project Management team


C.

Business Case


D.

Project Initiation Documentation


Expert Solution
Questions # 2:

Which of the following management products ARE updated as part of Managing a stage boundary?

1. Business Case

2. Benefits Review Plan

3. Configuration Item Records

4. Project Brief

Options:

A.

1, 2, 3


B.

1, 3, 4


C.

1, 2, 4


D.

2, 3, 4


Expert Solution
Questions # 3:

The Calendar project was delivered as originally planned, and Is now preparing for planned closure.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Question # 3


Expert Solution
Questions # 4:

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

Options:

A.

Scope, People & Resources, Benefit


B.

Scope, Risk, Product


C.

Risk, Benefit, Product


D.

Scope, Risk, Benefit


Expert Solution
Questions # 5:

Which principle is supported by the activity Evaluate the Project?

Options:

A.

Continued Business Justification


B.

Defined roles and responsibilities


C.

Learn from experience


D.

Manage by stages


Expert Solution
Questions # 6:

Which of the following activities is NOT an action of preparing for planned closure?

Options:

A.

Update the project plan with actual


B.

Update the Project Management Team


C.

Request a product status account


D.

Confirm project has delivered what is defined in Project Product Description


Expert Solution
Questions # 7:

Which of the following activities could trigger the production of an exception plan?

Options:

A.

Review Stage status


B.

Giving ad hoc direction


C.

Escalating a project issue


D.

Report stage end


Expert Solution
Questions # 8:

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Question # 8

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Question # 8

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Budgets section?

Options:

A.

Amend entry 15 because it should also include the cost of management activities.


B.

Delete entry 16 because timescales should NOT be shown under the heading of budgets.


C.

Delete entry 17 because the risk budget should be shown in the Risk Management Strategy.


D.

Add 'Change budget - £500'.


E.

Add 'Cost tolerance - +£6k 1-£6k


Expert Solution
Questions # 9:

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Question # 9

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Question # 9

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Planning assumptions section?

Options:

A.

No change to entry 8 because this cannot be confirmed until all of the label designs entries have been received and an assessment made.


B.

Move entry 8 to External dependencies because the label designs are created outside of the scope of the project.


C.

Delete entry 9 because the photo session schedule should have been approved as part of stage 2.


D.

Move entry 9 to External dependencies because the photo session schedule is created by the professional photographer.


E.

Delete entry 10 because the inclusion of different members from the Engineering team in each photo should be shown in the Product Description for the photos.


Expert Solution
Questions # 10:

Having completed designing the plan, in which order should the next steps take place to produce a plan?

1. Prepare Estimates

2. Define and analyze Products

3. Prepare the schedule

4. Identify activities and dependencies

Options:

A.

2, 4, 3, 1


B.

4, 2, 1, 3


C.

4, 3, 2, 1


D.

2, 4, 1, 3


Expert Solution
Viewing page 1 out of 8 pages
Viewing questions 1-10 out of questions