Prince2-Practitioner Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

Which of the following statements is FALSE regarding the Continued Business Justification?


A.

The justification for the project must remain the same throughout the project.


B.

The justification for the project should remain vabd.


C.

The justification for the project may change.


D.

If the project is no longer justified it should be stopped.