Questions # 31:

Which is an advantage of frequent releases?

Options:

A.

Releases can be used to replace management stages


B.

A ‘one-team’ culture in the project team is encouraged


C.

Configuration management becomes less important


D.

The delivery team becomes more experienced at product handover


Expert Solution
Questions # 32:

Which of the following is used to monitor progress?

Options:

A.

Delegation matrix


B.

Swarming


C.

T-shirt sizing


D.

Burn-down chart


Expert Solution
Questions # 33:

Which statement explains how the ‘learn from experience’ principle is applied in an agile context?

Options:

A.

It focuses on the prioritization and decomposition of requirements


B.

It integrates releases within management stages


C.

It is supported by the ‘inspect and adapt’ concept


D.

It provides guidance on mapping PRINCE2 roles to an agile environment


Expert Solution
Questions # 34:

Why are team working agreement produced?

Options:

A.

To create structure so that the team manager can assess individual performance


B.

To evolve the effectiveness and behaviors of the self-organizing team by agreeing values


C.

To make the team rules visible to the project manager for monitoring purposes


D.

To ensure that the delivery team members comply with company policy


Expert Solution
Questions # 35:

How should team working agreements be created?

Options:

A.

By the supplier subject matter expert agreeing what should be included


B.

By the customer representative deciding what should be included


C.

By team members agreeing on what should be included


D.

By the project manager deciding what should be included


Expert Solution
Questions # 36:

What is used to address aspects of project and product development such as problem solving and release planning?

Options:

A.

Delegation matrix


B.

Project log


C.

Agilometer


D.

Agile workshops


Expert Solution
Questions # 37:

Which statement about the ‘initiating a project’ process is CORRECT?

Options:

A.

The initiation stage plan should form part of the project plan


B.

The impact of frequent releases on quality management should be assessed


C.

The process should take more time than usual for disruptive projects


D.

The project solution should be documented in detail in the project product description


Expert Solution
Questions # 38:

Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

Options:

A.

Defined roles and responsibilities


B.

Continued business justification


C.

Learn from experience


D.

Tailor to suit the project


Expert Solution
Questions # 39:

Which two statements about tailoring the business case in an agile environment are CORRECT?

1. It should be unnecessary because products of the highest value will be delivered first.

2. It should identify the minimum viable product and when it will be delivered.

3. It should take into account that the scope may be reduced during the course of the project.

4. It should show the features, the order in which they will be delivered and any dependencies.

Options:

A.

1 and 2


B.

2 and 3


C.

3 and 4


D.

1 and 4


Expert Solution