PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 37 Topic 4 Discussion

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 37 Topic 4 Discussion

PRINCE2-Agile-Foundation Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

Which statement about the ‘initiating a project’ process is CORRECT?


A.

The initiation stage plan should form part of the project plan


B.

The impact of frequent releases on quality management should be assessed


C.

The process should take more time than usual for disruptive projects


D.

The project solution should be documented in detail in the project product description