PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 38 Topic 4 Discussion

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 38 Topic 4 Discussion

PRINCE2-Agile-Foundation Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?


A.

Defined roles and responsibilities


B.

Continued business justification


C.

Learn from experience


D.

Tailor to suit the project


Get Premium PRINCE2-Agile-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.