Questions # 21:

An audit team leader arrives at a steel fabrication organisation that manufactures stairways to carry out a Stage2 certification audit. At a meeting with the OHSMS Manager, she is told that they have won their biggest contact from a construction organization to manufacture and install stairways.

During the audit, a team member found that several employees had suffered hand injuries over several months due to handrail welds not being property polished. The OHSMS Manager blames the new employees they had to take on because of the big contract. The auditor raises a nonconformance against clause 10.2 erf ISO 45001.

In relation to the nonconformity raised by the auditor and in line with the policy of the certification body, the audit team raise improvement opportunities in the audit report.

Which three of the options would represent acceptance opportunities for improvement in the report?

Options:

A.

A quality control programme could involve non-destructive testing of the welded handrails


B.

Operational planning activities may benefit from an improved risk based approach based on international standards tor risk management.


C.

A first aid station could be located next to the handrail polishing operation.


D.

Additional internal audits of the OHS management system may reduce production problems.


E.

All workers should be given competence test.


F.

The induction programme for new employees could include an awareness training video in health and safety.


G.

The requirement for wearing protective gloves could be extended to shop floor workers across all operations.