Questions # 1:

There are five teams working on a product. How many Product Owners would there be? (Choose the best answer)

Options:

A.

5


B.

1


C.

Let the team decide


D.

It depends


Expert Solution
Questions # 2:

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog. True or False?

Options:

A.

True


B.

False


Expert Solution
Questions # 3:

How important is it for a Product Owner to order Product Backlog items by value points? (Choose the best answer)

Options:

A.

Using value points is the ultimate way for a Product Owner to predict the value that the product will provide.


B.

It is a good practice, keeping in mind that market reception is the best measure of value.


C.

Calculating value points is an upfront approach that conflicts with the empiricism of Scrum, and is therefore not acceptable.


Expert Solution
Questions # 4:

The Product Owner’s authority to change and update the Product Backlog is unlimited, except for: (Choose the best answer)

Options:

A.

Decisions by the CFO, the CEO, or the board of directors.


B.

Nothing. The entire organization must respect a Product Owner’s decisions.


C.

Decisions by the chief program manager.


D.

Technical and architectural work that needs to be done first, as indicated by the chief enterprisearchitect.


E.

High impact changes that have not been approved by the change request board.


F.

Work for which impediments exist that the Scrum Master still needs to resolve.


Expert Solution
Questions # 5:

Who is responsible for maximizing the value of the product? (Choose the best answer)

Options:

A.

Scrum Master


B.

Product Owner


C.

Senior Executives


D.

Developers


Expert Solution
Questions # 6:

When is the Sprint Backlog created? (Choose the best answer)

Options:

A.

In advance of Sprint Planning


B.

During the Sprint


C.

Backlog refinement


D.

Sprint Planning


Expert Solution
Questions # 7:

True or False: A first Sprint can start before the Product Owner has a complete and exhaustive Product Backlog in place.

Options:

A.

True


B.

False


Expert Solution
Questions # 8:

What pre-conditions must be fulfilled in order to allow Sprint Planning to begin? (Choose the best answer)

Options:

A.

A fully refined Product Backlog


B.

Formal budget approval to conduct another Sprint


C.

A clear and non-negotiable Sprint Goal


D.

A clear but negotiable business objective for the Sprint


E.

Enough "Ready" Product Backlog to fill the Sprint


F.

There are no such pre-conditions


Expert Solution
Questions # 9:

What two phrases best describe the relationship of the Product Owner and the Developers? (Choose the best two answers)

Options:

A.

They should work apart as much as possible in order to keep the concerns of business and technology separated.


B.

They collaborate often so the Product Owner can make informed decisions in balancing effort and value of Product Backlog items.


C.

The Product Owner should be with the Developers full-time to grow a deep understanding of the technology being used.


D.

They collaborate often so the Developers build Increments keeping end-user and stakeholder concerns in mind.


E.

They should share no more than the Sprint Planning and the Sprint Review meeting.


Expert Solution
Questions # 10:

Who is responsible for clearly expressing Product Backlog Items? (Choose the best answer)

Options:

A.

The Product Owner.


B.

The Scrum Master.


C.

The Scrum Master, or the Scrum Master may have the Developers do it.


D.

The business analyst who represents the Product Owner in the Developers.


Expert Solution