Question #: 8
Topic #: 1

What pre-conditions must be fulfilled in order to allow Sprint Planning to begin? (Choose the best answer)


A.

A fully refined Product Backlog


B.

Formal budget approval to conduct another Sprint


C.

A clear and non-negotiable Sprint Goal


D.

A clear but negotiable business objective for the Sprint


E.

Enough "Ready" Product Backlog to fill the Sprint


F.

There are no such pre-conditions