Scrum imposes no formal pre-conditions for Sprint Planning beyond the Sprint starting. TheScrum Guidestates: "Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint."
A:A fully refined backlog isn’t required; refinement is ongoing.
B:Budget approval isn’t a Scrum concept.
C, D:The Sprint Goal is defined during, not before, Sprint Planning.
E:Some "Ready" items help, but it’s not mandatory; planning can refine items.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.