Questions # 1:

ZYXS service management currently operates a Change Approval Forum (CAF): which is chaired by the ZYXS Service Management and Service Desk Lead, and is meant to be attended by user representatives from each ZYX company.

-In the new SIAM model ZYX is considering using SIAMRUS as the service integrator

-ZYX plans to keep all current service providers, renegotiating and extending contracts where necessary.

-OUTSCO will continue to provide the services for users in ZYXUK

-ZYXS, ZYXD, and the application development team from ZYXUK will become internal service providers

The SIAMRUS SIAM model includes a process model for change management. In this model. SIAMRUS will hold an Integrated Change Advisory Board (ICAB) meeting every two weeks, where proposed changes to the services and systems will be reviewed before approval SIAMRUS will mandate the use of their change management toolset by all service providers

The CIO is concerned that some of the current service providers may not comply with the SIAMRUS process model for change management

Which organizations are most likely to not comply and why?

Options:

A.

CADSCO, FIELD$CO and MAIL$CO. because commodity service providers provide services to multiple customers


B.

OUTSCO, because they use a commodity cloud-based service to monitor the ZYXUK networks and infrastructure


C.

ZYXS, because their Service Management and Service Desk Leadis the chair of the current ZYXS CAF


D.

ZYXUK, because there is no need for the development team to attend the ICAB as they are an internal service provider


Questions # 2:

What best describes ZYX's strategic drivers for transitioning to a SIAM model?

Options:

A.

To enable the design implementation operation and improvement of integrated end-to-end services

•To ensure that these services are aligned with the ZYX corporate objectives, and allow problematic legacy systems to be retired


B.

To reduce the overhead and cost of managing an increasing number of service providers across the different ZYX companies

-To reduce the incidence of contract overlap, where more than one provider is being paid to deliver the same service within ZYX


C.

To reduce the risk of the service providers operating in silos, focused on their own targets rather than the wider end-to-end service

-To promote collaboration between providers in seeking ways to reduce IT operating costs and enable Agile development of new services C .


D.

To reduce the costs of operating IT. while at the same time ensuring that agreed service levels are met

-To enable IT capabilities that support agility and rapid expansion of the ZYX business into new geographical areas


Questions # 3:

What is unlikely to be included in the outline business case for NEWGEN?

Options:

A.

Boundanes of responsibilities


B.

Measurements of benefits


C.

Procedures from internal providers


D.

Proposed future services


Questions # 4:

ZYXS has been selected as the service integrator. They will also provide some hosted application services, using ZYXD as a subcontractor. ZYXS will also provide a central service desk for the SIAM ecosystem.

Considering ZYXS, which factor is most critical to the success of SIAM?

Options:

A.

A service agreement between ZYXH and ZYXD


B.

Clearly defined roles and responsibilities


C.

Management of process outcomes instead of activities


D.

Well-conceived SIAM strategy


Questions # 5:

The SIAM strategy for ZYX has been agreed:

-There will be a mix of new service providers and continuing existing service providers

-An external service integrator will be appointed

-ZYXS will provide the service desk.

-An agreement has been reached with OUTSCO to extend their contract to provide services to ZYXUK by two years

As key activities for the critical path to implement the SIAM model for ZYX, three parties must be transitioned into the SIAM model (listed in random order):

-continuing service providers

-the service integrator

-new service providers

In this instance, which sequence of activities offers the least risk to continuity of service for all ZYX companies'?

Options:

A.

All parties at the same time


B.

First the continuing service providers, then the service integrator and the new service providers last


C.

First the service integrator, then the new service provider, and the continuing service providers last


D.

First the service integrator, then both continuing and new service providers at the same time


Questions # 6:

ZYX has implemented a SIAM structure, appointing SIAMRUS as the service integrator.

The SIAM strategy is to consolidate to a smaller number of service providers over time as existing contracts expire Until then. ZYX wants all current service providers to be part of the SIAM ecosystem.

What should ZYX do?

Options:

A.

Communicate the SIAM strategy and instruct SIAMRUS to speak to all service providers to explain their role


B.

Draw up a collaboration agreement across all service providers setting out how they will work together


C.

Put a clause in service provider contracts that SIAMRUS is acting on behalf of ZYX or negotiate themselves


D.

Write to all the service providers informing them that SIAMRUS has been appointed as the service integrator


Questions # 7:

The CEO has asked SIAMRUS to assist in the Discovery and Strategy stage. Given this stage, SIAMRUS is not appointed as the service integrator yet. The first task assigned to SIAMRUS is to analyze the current ZYX services and service providers.

OUTSCO has refused to provide any information to SIAMRUS because they are a competitor SIAMRUS still needs information to create a baseline assessment

What is the best approach for SIAMRUS to get the necessary information about OUTSCO and its services'?

Options:

A.

Analyze the current and historic OUTSCO related incidents recorded in the ZYXS service desk tool


B.

Ask the ZYXH contract governance team to formally instruct OUTSCO to provide the information


C.

Rely on the analysis of services and providers included in the report prepared by the CIO


D.

Review the OUTSCO contract and performance reports with the ZYXUK service delivery managers


Questions # 8:

The ZYXS IT Director has proposed to the CIO that ZYXS should be the service integrator in the new SIAM model. The CIO wants to validate if the necessary capabilities exist in ZYXS. The CIO has asked SIAMRUS to perform the assessment.

What is the first activity that SIAMRUS should carry out?

Options:

A.

Compare the ZYXS service integration capabilities with the SIAM objectives and the target SIAM model


B.

Assess the existing capabilities of each team in ZYXS and determine if they are at the required maturity


C.

Identify and then map the stakeholders, process owners and managers for all services across ZYX


D.

Prepare a heat map to provide a graphical summary of capabilities and show it to the CIO


Questions # 9:

The CEO of ZYX is proposing a big bang approach for the SIAM implementation.

For what reason does the CEO propose this?

Options:

A.

ZYX has a number of smaller contracts ending within the next few months


B.

ZYX needs to quickly achieve organizational changes in different business units


C.

ZYX would have a clean break from legacy issues including undesirable working practices


D.

ZYX is unwilling to accept the increased risk of a phased implementation


Questions # 10:

ZYX has used a phased approach for implementing the SIAM model

-ZYXS is the service integrator and provides the service desk for the SIAM ecosystem

-NETSCO had all network services transitioned to them

-OUTSCO has been selected to provide hosting services

The next phase is to transition all services currently hosted by ZYXS and ZYXD to OUTSCO Due to time pressures, it has not been possible to test how the services will perform after transition.

The ZYX CEO is concerned about the risks to the services and the ability of ZYX to be able to carry out its business activities She wishes that an early life support (ELS) function is implemented

What approach should be taken to resolve incidents and problems caused by the transition of services?

Options:

A.

Complete the transition over a weekend when the number of people using the services will be low


B.

Ensure that the ZYXS service desk is fully briefed and ready to handle any increase in call and incident volumes


C.

Establish a data room containing all information about the services so that facts and data can be quickly checked


D.

Set up a short-term function with staff from BANKSCO, ZYXS. ZYXD: ZYXG. NET$CO and OUTSCO