In a new building, which of the following is an effective way to confirm a building’s performance compared with performance goals, design specifications, and the Owner’s Project Requirements?
Commissioning (Cx) ensures that building systems meet the Owner’s Project Requirements (OPR) and function as intended. It is required under EA Prerequisite: Fundamental Commissioning.
“Commissioning verifies that the building’s energy-related systems are installed, calibrated, and perform according to the owner’s project requirements.”
— LEED v4 BD+C Reference Guide, EA Prerequisite: Fundamental Commissioning