Scrum Master Certified (SMC) SMC Question # 18 Topic 2 Discussion

Scrum Master Certified (SMC) SMC Question # 18 Topic 2 Discussion

SMC Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

Listed below are some risks and issues that might be encountered during the course of a project. Identify

which of the following are risks (not issues).

A) After extensive training, marketing representatives might still not be ready to take orders after the project is

launched.

B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

C) Funding was not approved.

D) Requirements, as currently defined, are unclear.


A.

Only В


B.

A and C


C.

В and D


D.

A and B


Get Premium SMC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.