The Chief Scrum Master plays an important role during the Retrospect Project process. By being a part of the

Retrospect Project Meeting, he/she provides valuable inputs mainly to identify, document, and internalize the

lessons learned during the process. What is an output of this process?


A.

Agreed Actionable Improvements.


B.

Agreed Actionable Schedule.


C.

Agreed Actionable Lessons.


D.

Agreed Actionable Objectives.