The decision to implement pair programming in future iterations is a team-level improvement action that stems from reflecting on their current processes and identifying areas for enhancement. This is best captured during the team's retrospective:
Retrospective Purpose:The retrospective is a regular meeting where the team reflects on what went well, what didn’t, and what could be improved.
Action Items:Decisions and action items, such as adopting pair programming, are documented in the retrospective notes to ensure they are followed up in future iterations.
Continuous Improvement:Capturing this in the retrospective notes ensures the team is committed to continuous improvement and has a clear record of their decisions and plans for process enhancements.
SAFe Scrum Master References:
SAFe Advanced Scrum Master Training Material, Chapter on Team Retrospectives.